Table 2.2          Detailed Dredging Quantity

Date

Dredged Quantity (in-situ, m3)

Portion A

Portion B

Portion C

Portion E

Zone (Maximum Allowable Daily Dredged Rate)

Max Allowable Daily Dredged Rate=4000

23/01/2014

2A2: 650 (650)

0

1200

4000

0

24/01/2014

2A1: 750 (750)

0

800

3500

0

25/01/2014

3A: 400 (1600)

4B: 800 (1600)

1600

4000

0

26/01/2014

2A2: 650 (650)

0

1100

4000

0

27/01/2014

2A3: 800 (1500)

1B: 800 (1100)

800

3500

0

28/01/2014

0

0

2800

0

1500

29/01/2014

0

0

2400

3500

0

30/01/2014

3A: 800 (1600)

0

1200

4000

0

31/01/2014

0

0

2400

4000

0

1/2/2014

0

0

2400

4000

0

2/2/2014

0

0

2800

3500

0

3/2/2014

0

0

2400

3500

0

4/2/2014

0

0

2400

4000

0

5/2/2014

0

0

2800

0

0

6/2/2014

0

0

1200

0

0

7/2/2014

0

0

2400

0

0

8/2/2014

0

0

2400

3000

0

9/2/2014

0

0

2400

3000

0

10/2/2014

0

0

2800

3308

0

11/2/2014

0

0

2000

3000

0

12/2/2014

0

0

2800

3500

0

13/02/2014

0

0

2800

4000

0

14/02/2014

0

0

1200

4000

0

15/02/2014

0

0

0

1000

0

16/02/2014

0

0

0

2000

0

17/02/2014

0

0

0

500

0

18/02/2014

0

0

0

0

0

19/02/2014

0

0

0

0

0

20/02/2014

0

0

0

0

0

21/02/2014

0

0

0

0

0

22/02/2014

0

0

0

0

0